New Delhi, November 27, 2026 : Jammu and Kashmir Minister for Power Development Department (PDD), Ali Mohammad Sagar, has sought a dedicated financial package from the Union Government to modernise the Union Territory’s power sector, address critical infrastructure gaps and ensure reliable electricity supply during the harsh winter months.
Sagar raised the issue during the State Ministers’ Conference on Power in New Delhi, chaired by Union Minister for Power Manohar Lal. Interacting with the Group of Ministers, he highlighted the geographical, climatic and financial challenges facing Jammu and Kashmir’s electricity sector and submitted a detailed memorandum outlining the region’s key requirements.
The proposed package aims to strengthen distribution and transmission networks, reduce power losses, accelerate hydropower development, improve energy storage and enhance the resilience of electricity infrastructure against extreme weather events.
Winter Power Deficit Emerges as a Major Concern
Highlighting the mounting pressure on the power sector during winter, Sagar said Jammu and Kashmir’s peak electricity demand reached approximately 3,362 MW during the previous winter, comprising 1,456 MW in the Jammu division and 1,906 MW in Kashmir.
For winter 2026–27, the anticipated restricted demand is estimated at around 3,450 MW, with a projected supply shortfall ranging between 600 MW and 1,300 MW.
The Minister pointed out that electricity demand rises sharply during winter, precisely when hydropower generation declines, creating additional pressure on the region’s power supply arrangements.
He urged the Centre to provide additional unallocated electricity, ensure predictable power allocations and continue or enhance the additional 329 MW allocation for December 2026 to February 2027.
Sagar also sought support for affordable long-term power procurement and electricity banking arrangements with neighbouring states, including Punjab and Uttar Pradesh, to help bridge seasonal supply gaps.
Distribution Companies Show Improvement
The Minister highlighted improvements in revenue collection and operational performance by Jammu Power Distribution Corporation Limited (JPDCL) and Kashmir Power Distribution Corporation Limited (KPDCL).
According to the figures presented, combined revenue realisation increased from approximately ₹3,060 crore in 2021–22 to ₹5,290 crore in 2025–26, representing growth of nearly 73 per cent.
Aggregate technical and commercial (AT&C) losses also declined substantially:
- JPDCL: From 49.82 per cent to 27.13 per cent.
- KPDCL: From 65.61 per cent to 33 per cent.
The Minister further noted improvements in the gap between the average cost of electricity supply and the average revenue realised, indicating progress towards improving the financial sustainability of the distribution companies.
Smart Metering and Infrastructure Modernisation
Under the Revamped Distribution Sector Scheme (RDSS), 14.07 lakh smart meters have been sanctioned, of which approximately 12.25 lakh had been installed as of November 19, 2026.
Distribution-strengthening and loss-reduction works worth ₹4,708.52 crore have also been sanctioned, with substantial physical progress reported across both distribution companies.
Sagar sought continued Central assistance for replacing ageing and overloaded transformers, upgrading 33/11 kV infrastructure, installing additional substations and strengthening low-tension distribution networks.
He also called for alternative power-feeding arrangements, underground and insulated cabling in vulnerable locations and dedicated enforcement wings to curb electricity theft and unauthorised consumption.
The Minister stressed that modernisation must address not only infrastructure deficiencies but also operational efficiency and the persistent challenges of power distribution in remote and difficult terrain.
Jammu and Kashmir’s Untapped Hydropower Potential
Hydropower development featured prominently in the memorandum, with Sagar highlighting Jammu and Kashmir’s estimated hydropower potential of 14,635 MW, of which approximately 3,540 MW has been harnessed so far.
He referred to the ongoing Pakal Dul, Kiru, Kwar and Ratle hydropower projects, which together have an aggregate capacity of approximately 3,563.5 MW.
The Government aims to increase installed hydropower capacity to around 10,975.65 MW by 2035.
To accelerate development, Sagar sought Central assistance through grants, concessional financing and viability gap funding. He also called for support for geological investigations and the preparation of detailed project reports.
The proposed Jammu and Kashmir Hydro Power Policy 2026 was highlighted as an important step towards encouraging investment and expanding hydropower development, including through greater private-sector participation.
Battery Storage Proposed to Manage Peak Demand
Emphasising the need for energy storage to manage peak-hour requirements and integrate renewable energy, the Minister outlined a proposal to develop Battery Energy Storage Systems (BESS) with a capacity of 250 MW/1,000 MWh over three years.
The proposal envisages scaling up storage capacity to 1,000 MW/4,000 MWh by 2031.
Such systems could help store electricity when available and release it during periods of high demand, improving supply flexibility and supporting the integration of renewable energy sources.
Transmission Network Expansion and Grid Resilience
Sagar also highlighted the ongoing transformation of the Jammu and Kashmir Power Transmission Corporation Limited (JKPTCL).
The corporation has a transformation capacity of approximately 12,875 MVA, with another 3,766 MVA in the pipeline.
He sought Central support for new transmission lines, grid substations, transformer augmentation, modern digital substations and stronger transmission corridors to accommodate rising electricity demand.
Given the region’s exposure to heavy snowfall, avalanches, landslides, cloudbursts and flash floods, the Minister emphasised the need to make power infrastructure more resilient to natural disasters.
He proposed a dedicated Himalayan Power Infrastructure Resilience Programme, including the procurement of Emergency Restoration System (ERS) units to speed up the restoration of damaged transmission infrastructure.
While seven ERS units have already been procured for Jammu, Sagar highlighted the requirement for another 15 units for Jammu and 10 for Kashmir.
Digitalisation and Specialised Training
The Minister stressed the importance of digitalisation, smart-grid technologies, cybersecurity and modern operational systems to improve the efficiency and reliability of electricity networks.
He also proposed establishing two dedicated Power Training Colleges, one each in the Jammu and Kashmir divisions, to strengthen technical expertise and build capacity among power-sector personnel.
According to Sagar, reliable and affordable electricity is essential to support industrial development, tourism, horticulture, cold-chain facilities, healthcare services and the emerging electric mobility ecosystem across Jammu and Kashmir.
Joint Working Group Proposed for Time-Bound Action
Concluding his presentation, Sagar urged the Union Government to consider a dedicated Jammu and Kashmir Power Sector Development and Modernisation Package combining grants, concessional loans, viability gap funding and project-based assistance.
He also proposed constituting a joint working group comprising representatives of the Government of India and the Jammu and Kashmir Government to examine the submitted proposals and facilitate their time-bound implementation.
The Minister expressed confidence that sustained Central support would help address the region’s structural power-sector challenges, strengthen energy security and establish a more modern, resilient and financially sustainable electricity system.
The key challenge now is to translate the proposed financial support and infrastructure plans into measurable improvements in winter electricity availability, distribution efficiency and long-term energy security for the people of Jammu and Kashmir.
Truth Prevail — Bringing You the Headlines That Matter!